The first dredging project at Deep Creek Lake will begin in October 2023 and is predicted to be completed by mid-winter. This $2.2M pilot project was funded by the State of Maryland and will remove approximately 15,000 cubic yards of sediment from Arrowhead Cove. It’s estimated that this will add 1-4 ft of depth to the cove, allowing for [...]
Pilot Dredging Project Beginning at Deep Creek Lake